Boeing’s long-delayed 777X program has encountered an unusual problem: some of its largest customers do not want the aircraft it built first. Emirates has rejected its earliest examples, while Lufthansa is negotiating over which aircraft it will accept. The issue is the extensive modifications necessary to bring older airframes up to current production standards, following years of development and certification delays.
However, Southwest Airlines is taking a different approach with the Boeing 737 MAX 7. Following the aircraft’s certification in August, the carrier is preparing to accept 27 previously manufactured examples that have spent years in storage. The contrasting responses raise an interesting question: why is Southwest willing to take aircraft built before certification when major 777X customers are rejecting theirs?